The Questions We Still Need Answered

These are the questions this research hasn't been able to answer yet — not because they don't matter, but because the information isn't public, or at least not where we've been able to find it. This isn't a complete list. If you're at a meeting where someone from Aqua WSC, the county, or EdgeConneX can answer one of these on the record, that's real progress. If you know something these don't, tell us.

Help Us Help You. Take this to a meeting and report back.

Report Back

What's Actually Happening

  1. Is there a signed, binding community benefit agreement the public can read — not verbal assurance?
  2. How many cooling loops does this facility run — does any use evaporative cooling, and if so, what's the expected annual water consumption, not the contracted maximum?
  3. Is the full 350 LUE billed regardless of actual consumption, or only for water actually used?
  4. Will the second campus (6682 FM 535) require its own separate water allocation, and how much?
  5. Campus 1 has 4 buildings proposed, and only Building 1 currently has a signed agreement — will the other 3 also be data centers, and will each need its own individual water contract, or will they draw on Building 1's allocation?
  6. Has a well-interference study been conducted for neighboring private wells outside Aqua WSC's service area?
  7. Does Aqua WSC's contract with this facility include the drought curtailment required under Texas Water Code §11.039, and would a cutback be measured by percentage or by gallons?
  8. Has this project sought or received any federal "Qualifying Project" or national security designation?
  9. Does the addendum/assignment process used for Building 1 let future phases avoid the same public hearing scrutiny the original building received?
  10. Was independent environmental review required for this project, or did the county accept the applicant's own self-certification of "no expected impact" with no category-specific detail?

What a Good Deal Requires

  1. Aqua WSC's own June 25, 2026 statement says infrastructure upgrade costs are borne by the developer, not ratepayers — is that holding true in practice, and is it enforceable, or just a stated intention?
  2. What public revenue is being deferred or forgone under the 75% tax abatement, and who absorbs that difference?
  3. What enforcement mechanism exists if the facility exceeds its contracted water allocation?
  4. How will actual water consumption be measured, reported, and independently verified over time?
  5. What happens to existing water and tax agreements if the facility is sold to a third-party company?
  6. Does it include a hard water-use cap, not just a contracted maximum "up to" figure?
  7. The application left the percentage of jobs going to Bastrop County residents as "TBD" — is there any mechanism requiring that number to be finalized, and if so, when?
  8. Is there a penalty or clawback if the company misses its commitments?